International Competitive Procurement · Request for Bids (Two-Envelope, Without Prequalification)

Design, Supply, Installation, Testing, Commissioning and Handover of the Approx. 121 km Songo–Matambo 400 kV Transmission Line, Mozambique

Ref.MZ-EDM-574541-CW-RFBIssued2026-10-13Deadline2026-11-30
Mozambique
Country
Approx. 121 km of 400 kV overhead transmission line (Songo substation to Matambo substation)
Line Scope
Design, supply, installation, testing, commissioning and handover (EPC)
Contract Nature
2026-11-30 14:00 (local time)
Bid Deadline

01Project Overview

Project Name
Songo–Matambo 400 kV Transmission Line Project (Lot 1: Transmission Line) — design, supply, installation, testing, commissioning and handover
Reference
RFB No. MZ-EDM-574541-CW-RFB; World Bank procurement notice No. OP00474699; grant No. E303-MZ
Country
Republic of Mozambique
Employer
Electricidade de Moçambique, E.P. (EDM)
Parent Project
Green Energy Corridors Project, World Bank project ID P179797
Financing
World Bank grant financing for the Green Energy Corridors Project (grant No. E303-MZ), disbursed by the Direct Payment method except for payments the contract provides to be made through a letter of credit
Procurement Method
International competitive procurement by Request for Bids; a two-envelope process without prequalification, under the World Bank Procurement Regulations for IPF Borrowers, September 2025 edition
Language
English
Source
World Bank procurement notice OP00474699 (tender No. MZ-EDM-574541-CW-RFB), employer Electricidade de Moçambique (EDM), published 13 Oct 2026, verified 15 Oct 2026: https://projects.worldbank.org/en/projects-operations/procurement-detail/OP00474699
Background Source
World Bank project page P179797: https://projects.worldbank.org/en/projects-operations/project-detail/P179797; Electricidade de Moçambique: https://www.edm.co.mz/; Ministry of Mineral Resources and Energy of Mozambique: https://www.mireme.gov.mz/

02Project Background

The Green Energy Corridors Project is financed by the World Bank under project ID P179797, with a commitment amount of US$300 million, approved by the World Bank Board on 29 March 2024 and scheduled to close on 30 June 2030. The borrower is the Republic of Mozambique and the implementing agencies are Electricidade de Moçambique (EDM) and the Ministry of Mineral Resources and Energy (MIREME). The project's objective is to strengthen the electricity network and increase regional power trade.

The project has three components. The first strengthens transmission infrastructure and finances the construction of a new 400 kV transmission line between Songo and Matambo via Cataxa, together with upgrades at the existing Songo and Matambo substations. The second enables renewable energy at scale through a coordinated national programme for competitive procurement and de-risking finance. The third improves sector governance to increase private sector participation and expand Mozambique's role in the Southern African Power Pool (SAPP) region.

This procurement falls under the transmission infrastructure component. The notice states that the Government of Mozambique has received financing from the World Bank towards the cost of the Green Energy Corridors Project and intends to apply part of the proceeds towards payments under this contract, which covers the 400 kV overhead transmission line from Songo substation to Matambo substation over a period of 30 months.

03Scope of Work & Technical Specifications

ItemContent
Contract ScopeSongo–Matambo 400 kV Transmission Line Project (Lot 1: Transmission Line)
Line LengthApproximately 121 km of 400 kV overhead transmission line from Songo substation to Matambo substation
WorksDesign, supply, installation, commissioning and handover of the line
Contract Duration30 months
LotsThe notice states Lot 1 covers the transmission line
Associated WorksThe notice describes the contract as covering the transmission line and associated works; upgrades at the existing Songo and Matambo substations are procured separately under the same project
Supply and Construction ResponsibilityThe contractor is responsible for the plant design, supply of equipment, installation, testing, commissioning and handover of the line and associated works
← Swipe to view the full table →

04Key Commercial Terms

ItemContent
PaymentPayments are processed by the Borrower using the Direct Payment disbursement method under the World Bank's Disbursement Guidelines for Investment Project Financing, except for payments the contract provides to be made through a letter of credit
Bid SecurityAll bids must be accompanied by a Bid Security Declaration; no bank-guarantee form of bid security is used for this procurement
Bidding DocumentThe bidding document in English may be requested free of charge upon submission of a written application to the Employer; the document may be inspected during office hours from 09:00 to 15:30 local time
Bid SubmissionElectronic bidding is not permitted; bids must be delivered in hard copy to the address indicated in the notice before the deadline, and late bids are rejected
Evaluation WeightingThe notice states that rated criteria, including technical and non-price factors, carry a weighting of 60 per cent, and bid cost 40 per cent
Performance Security and WarrantyPlant design and installation contracts of this type commonly require a performance security for a percentage of the contract price and provide for a defects liability period; this contract runs for 30 months, with the defects liability arrangements set out in the bidding document
← Swipe to view the full table →

05Bidder Qualification Requirements

01
Eligibility
Open to all eligible Bidders as defined in the World Bank Procurement Regulations for IPF Borrowers (September 2025 edition), with no restriction to Mozambican firms
02
Qualification Approach
This procurement is without prequalification; qualification requirements are verified by post-qualification during evaluation, with detailed financial, similar-experience and key-personnel requirements set out in the bidding document
03
Bid Form
Two-envelope bidding: the outer envelope is marked "ORIGINAL BID", and the inner envelopes are separately sealed and marked "TECHNICAL PART" and "FINANCIAL PART"
04
Bid Security
Bids must be accompanied by a Bid Security Declaration
05
Sanctions and Ineligibility
Bidders and their proposed subcontractors must not be subject to ineligibility or sanctions under the World Bank Procurement Regulations; the beneficial ownership disclosure requirements are checked during evaluation

06Key Milestones

13 Oct 2026
Notice Published
From the date of the notice, obtainable from the Employer during office hours 09:00 to 15:30 local time
Bidding Document Available
30 Nov 2026, 14:00 local time; the technical envelopes are opened publicly at that time, while the financial envelopes remain sealed and held for the second public opening
Bid Submission Deadline and Opening
30 months
Contract Duration

07Evaluation Criteria

Rated Criteria60%
  • Rated against the criteria set out in the bidding document for the line design, plant and technical performance, key personnel, construction arrangements and work methods, and environmental and social management
Bid Cost40%
  • The evaluated bid price is calculated from the price schedules in the bidding document and converted into a score, which is combined with the rated criteria score to determine the ranking of bidders
Contact Us
Room 1602, Tower D, Xiamen Sea World, Xiamen, China