The Electricity Services Improvement Project (Projet d'Amélioration des Services d'Électricité, PASEL) is supported by an IBRD loan under World Bank Project ID P501343, implemented by the Ministry of Energy and Hydraulics of the Republic of the Congo and Energie Electrique du Congo (E2C). Approved in June 2024 and scheduled to close in June 2028, it aims to improve the quality of electricity supply, improve distribution and sales performance and increase access to electricity, with investments covering the rehabilitation, strengthening and extension of distribution networks, the rehabilitation and construction of substations, and electricity facilities such as urban public lighting.
Within that project, the PASEL Project Implementation Unit has issued a request for expressions of interest for environmental and social impact assessment (ESIA) services for the MV/LV distribution network and public lighting works, inviting eligible consulting firms to express their interest. The assignment covers the preparation of two environmental and social impact assessments, one for Brazzaville and one for Pointe-Noire, covering the rehabilitation, strengthening and extension of MV/LV distribution networks, the rehabilitation and construction of MV/LV transformer substations, and the installation of 10,000 LED luminaires in the two cities. The notice states a total assignment duration of 70 calendar days.
| Item | Content |
|---|---|
| Scope of Services | Preparation of two environmental and social impact assessments (ESIA), one for Brazzaville and one for Pointe-Noire |
| Works Covered | Rehabilitation, strengthening and extension of MV/LV distribution networks; rehabilitation and construction of MV/LV transformer substations; installation of 10,000 LED luminaires in Brazzaville and Pointe-Noire |
| Description of Sub-projects | Detailed description of the sub-projects and of the activities envisaged |
| Areas of Influence | Delineation and characterisation of the direct and indirect areas of influence of the works |
| Analysis of Alternatives | Analysis of technical and environmental alternatives that avoid or reduce negative impacts |
| Baseline | Establishment of the environmental and social baseline situation of the intervention areas |
| Risks and Impacts | Identification and analysis of environmental, social, health and safety issues and of positive and negative, direct, indirect, cumulative and residual risks and impacts |
| Electricity-Specific Risks | Analysis of risks specific to electricity infrastructure, including electrocution, fire and accident risks, risks related to underground or exposed cables, and risks related to the occupation of electricity rights of way |
| Land and Economic Activities | Analysis of land issues related to substation sites and network rights of way, and identification of economic activities likely to be affected |
| Civil Works Risks | Analysis of risks related to civil works and excavation |
| Waste and Pollution | Analysis of risks related to the management of electrical and other hazardous waste, and assessment of soil and water pollution risks |
| Social Risks | Analysis of risks related to gender-based violence, sexual exploitation and abuse and sexual harassment; analysis of worker and community health and safety risks; analysis of biodiversity impacts where relevant; and analysis of risks related to cultural heritage |
| Public Consultation | Inclusive and participatory public consultations taking account of the specific concerns of women, youth and vulnerable persons |
| Environmental and Social Management Plan | Preparation of an Environmental and Social Management Plan (ESMP) for each city, defining environmental and social monitoring arrangements, a detailed budget for implementing the environmental and social measures, and institutional responsibilities for implementing the ESMP |
| Grievance Mechanism | Design of a grievance mechanism suited to the activities and consistent with the PASEL project grievance mechanism |
| Approval Documentation | Preparation of all documents needed for national validation and the World Bank's no-objection |
| Item | Content |
|---|---|
| Selection Method | Consultant's Qualification Selection (SQC), in accordance with the World Bank's Procurement Regulations |
| Assignment Duration | Total assignment duration of 70 calendar days |
| Terms of Reference | The detailed Terms of Reference (TDR) are available at the address given in the notice |
| Number of Copies | A written expression of interest submitted in four copies, comprising one original and three copies, accompanied by an electronic version on a USB key |
| Submission | The expression of interest must be delivered in person to the address given in the notice, marked with the notice number and the title of the assignment |
| Association and Sub-contracting | Consultants may associate with other firms to enhance their qualifications but must clearly indicate whether the association takes the form of a joint venture and/or sub-contracting; if the association is a joint venture, all members are jointly and severally liable for the entire contract if selected |
| Conflict of Interest | The notice draws attention to Section III, paragraphs 3.14, 3.16 and 3.17 of the World Bank Procurement Regulations on conflict of interest; consultants may not be engaged for assignments incompatible with their present or past obligations to other clients, or which could prevent them from serving the Borrower's best interests |
| Further Information | Further information may be obtained at the address given in the notice during office hours from Monday to Friday, 08:00 to 16:00 local time |