International — Request for Expressions of Interest (EOI)

Consultancy for APS and APD Studies for Least-Cost Electrification of 1,661 Localities within SENELEC's Perimeter and Preparation of Bidding Documents, PADAES Project, Senegal

Ref.34-CONS-PADAES-2026Issued2026-10-19Deadline2026-11-04
SENELEC perimeter, Senegal
Study Area
1,661 localities, about 4,391 km of MV lines
Study Scope
APS/APD design, economic and financial analysis and environmental and social studies
Services
2026-11-04 09:30 (local time)
Submission Deadline

01Project Overview

Project Name
Consultancy for the preparation of outline design (APS) and detailed design (APD) studies for the least-cost electrification of localities within SENELEC's perimeter, together with the preparation of the bidding documents
Reference
Expression of interest No. AMI N°35/2026; World Bank procurement plan reference 34-CONS-PADAES-2026; SENELEC procurement plan reference C_PADAES_338
Country
Republic of Senegal
Employer
Societe Nationale d'Electricite du Senegal (SENELEC)
Parent Project
Senegal Energy Access Scale Up Project (PADAES), World Bank project P176620
Source of Funds
International Development Association (IDA) Credits 70470-SN and 8066-SN; the notice records project credit and loan financing of USD 150 million
Procurement Method
Expression of interest for consulting services under the Quality and Cost Based Selection method, followed by a short list and request for proposals
Scope of Services
APS and APD technical studies, economic and financial analysis, environmental and social studies, and preparation of the bidding documents
Assignment Duration
An estimated 15 months, plus one month for the preparation of the consolidation report
Source
World Bank procurement notice (Sollicitation de Manifestations d'Interet) OP00469523, employer SENELEC, published 21 Sep 2026, clarification and postponement notice issued 19 Oct 2026, verified 21 Oct 2026: https://projects.worldbank.org/en/projects-operations/procurement-detail/OP00469523
Background Sources
Societe Nationale d'Electricite du Senegal (SENELEC), whose website records that it operates the public electricity service in Senegal, responsible for generation, transmission and distribution: https://www.senelec.sn/; World Bank project page for the Senegal Energy Access Scale Up Project (P176620), which records USD 160 million in commitments, board approval on 8 Mar 2022 and closing on 30 June 2029, implemented by SENELEC: https://projects.worldbank.org/en/projects-operations/project-detail/P176620

02Project Background

The Senegal Energy Access Scale Up Project (PADAES) is financed by the World Bank under project P176620. The World Bank project page records USD 160 million in commitments, board approval on 8 March 2022 and a planned closing date of 30 June 2029, implemented by the Societe Nationale d'Electricite du Senegal (SENELEC). The project aims to increase electricity access in Senegal, with investment focused on modernising and extending the national grid. The notice states that the study is set against Senegal's national ambition of achieving universal access to electricity by 2029, and that SENELEC, with the support of its development partners, has engaged strategic investments aimed at modernising and extending the national electricity network.

This expressions of interest is issued by the SENELEC procurement directorate for a feasibility study on least-cost electrification of localities within SENELEC's perimeter that are eligible for medium-voltage network extension, together with the preparation of the subsequent works bidding documents. The notice states that the study covers 1,661 localities and about 4,391 km of medium-voltage lines, divided by geography into two lots. Lot 1 covers 861 localities and about 1,236 km of medium-voltage lines in the regions of Thies, Diourbel, Fatick and Kaolack; Lot 2 covers 800 localities and about 3,155 km of medium-voltage lines in the regions of Ziguinchor, Sedhiou, Kolda, Tambacounda, Matam and Saint-Louis. A consultant may express interest in both lots but may be awarded only one; where a consultant ranks first in both lots, the lot with the greater medium-voltage line length is awarded. The assignment is expected to last 15 months, plus one month for the consolidation report.

On 19 Oct 2026 SENELEC issued a clarification and postponement notice for AMI No. 35/2026, moving the deadline for submission and opening of expressions of interest to Wednesday 4 November 2026, with the time and place of submission unchanged. The notice also confirms that only expressions of interest are required at this stage, submitted separately for each lot and identified as such in the letter of submission, and that technical and financial proposals are not required at this stage; evaluation will follow the criteria in point 5 of the original notice for each lot in order to establish a short list for each lot.

03Scope of Work & Technical Specifications

ItemContent
Overall ObjectivePrepare a feasibility study for the electrification of localities within SENELEC's perimeter that are eligible for least-cost electrification through medium-voltage network extension
Study Scope1,661 localities and about 4,391 km of medium-voltage lines
Lot 1Regions of Thies, Diourbel, Fatick and Kaolack: 861 localities and about 1,236 km of medium-voltage lines
Lot 2Regions of Ziguinchor, Sedhiou, Kolda, Tambacounda, Matam and Saint-Louis: 800 localities and about 3,155 km of medium-voltage lines
Technical StudiesPreparation of outline design (APS) and detailed design (APD), determination for each locality of the optimal connection route to the medium-voltage network so as to minimise technical losses and optimise investment cost, and assessment of the investment required to electrify all potential customers in the study area
Economic and Financial AnalysisEconomic and financial analysis of the project and a realistic schedule for the execution of the works
Environmental and Social StudiesEnvironmental and social impact studies (EIES) and environmental and social audits (AEI), together with resettlement plans (PR) where applicable
Bidding DocumentsPreparation of the bidding documents (DAO) for the award of the works contracts
Assignment DurationAn estimated 15 months, plus one month for the consolidation report
← Swipe to view the full table →

04Key Commercial Terms

ItemContent
Selection MethodQuality and Cost Based Selection (SFQC), with eligibility criteria, short-listing and the selection procedure following the World Bank Procurement Regulations for IPF Borrowers
SubmissionExpressions of interest are submitted in French, with one original and three copies delivered to the SENELEC procurement committee room and an electronic version sent by email to the addresses stated in the notice
Assignment DurationAn estimated 15 months from the effective date marked by notification of the contract, plus one month for the consolidation report
Bidding for Multiple LotsA consultant may express interest in both lots but may be awarded only one; where it ranks first in both, the lot with the greater medium-voltage line length is awarded
Conflict of InterestThe World Bank rules on conflict of interest apply, in accordance with the relevant provisions of the Procurement Regulations
Payment and SecurityConsultancy contracts of this kind usually provide for payment in instalments against deliverables and progress milestones, commonly provide no advance payment and require a performance security expressed as a percentage of the contract amount
← Swipe to view the full table →

05Bidder Eligibility Requirements

01
Legal Form
Must be a consultancy firm, company or joint venture; the same consultant may not participate both individually and as a member of a joint venture, nor in more than one joint venture
02
Professional Accreditation
Must be a technical and environmental studies consultant active in the electricity and environment sectors with proven rural electrification experience, and must hold the environmental studies accreditation issued by the Ministry of Environment and Ecological Transition of Senegal; in a joint venture at least one member must hold that accreditation
03
Years of Experience
At least 10 years of experience in the electricity sector and in technical studies of medium-voltage and low-voltage distribution networks
04
Environmental and Social Experience
Proven experience in conducting environmental and social studies
05
Attested References (2010-2025)
Must provide certificates of satisfactory performance for at least one assignment in each of the following: detailed design (APD) of electricity distribution projects of similar size; preparation of bidding documents (DAO) for MV and LV distribution network works; economic and financial evaluation of rural electrification projects; environmental and social evaluation of rural electrification projects financed by technical and financial partners such as the World Bank, AFD, EIB, EU, KfW or AfDB; preparation of resettlement plans in accordance with national regulations and World Bank Environmental and Social Standard 5 (NES 5); and at least one assignment in a francophone country of the sub-region
06
Software Capability
Must hold a licence for specialised geographic information system (GIS) software and demonstrate the ability to use it, and must hold a licence for planning software and demonstrate the ability to use it
07
Supporting Documents
Certificates of satisfactory performance or of services rendered must be provided for every declared experience; signed contracts do not replace such certificates

06Key Milestones

21 Sep 2026
Notice Published
19 Oct 2026
Clarification and Postponement Notice
21 Oct 2026, 09:30 local time
Original Deadline
4 Nov 2026, 09:30 local time, as extended
Submission Deadline
4 Nov 2026, 09:30 local time, at the same moment as the submission deadline
Opening of Expressions of Interest
Written requests to the SENELEC procurement directorate on business days from 07:30 to 16:30
Clarifications
An estimated 15 months, plus one month for the consolidation report
Assignment Duration
Contact Us