International Competitive Bidding (Two-Envelope)

Rehabilitation, Reinforcement and Extension of the Medium and Low Voltage Distribution Networks in Labe, Guinea, and Electrification of Surrounding Localities, Including Two Substations

Ref.GN-PAAEG - PHASE 2-537809-CW-RFBIssued2026-09-08Deadline2026-11-10
Labe, Guinea
Location
1,247.46 km
Low-Voltage Lines
65,796 connections
Service Connections and Metering
2026-11-10 10:30 (GMT)
Submission Deadline

01Project Overview

Project Name
Rehabilitation, reinforcement and extension of the medium and low voltage electricity distribution networks of the urban centre of Labe and electrification of surrounding localities
Reference
Bid reference GN-PAAEG - PHASE 2-537809-CW-RFB (World Bank procurement notice OP00467157)
Country
Republic of Guinea
Project Area
The urban centre of Labe and its surrounding localities
Project Type
Rehabilitation, reinforcement and extension of 30 kV medium voltage and low voltage distribution networks, together with new service connections
Contracting Authority
Electricité de Guinée (EDG-SA), under the Ministry of Energy of the Republic of Guinea
Source of Funds
Credits from the International Development Association (IDA), credit references IDA 7869-GN, 7870-GN and 7882-GN, under Phase 2 of the Guinea Electricity Access Scale Up Project (PAAEG 2, Project ID P511453)
Procurement Method
International competitive bidding under a two-envelope process without prequalification; equipment contract covering design, supply and installation
Contract Duration
Up to 24 months from the effective date of the contract
Language of Bid
French
Source
World Bank procurement notice page (https://projects.worldbank.org/en/projects-operations/procurement-detail/OP00467157) — notice OP00467157, bid reference GN-PAAEG - PHASE 2-537809-CW-RFB, published 8 Sep 2026, verified 24 Sep 2026
Background Sources
World Bank project detail page, Guinea Electricity Access Scale Up Project Phase 2 (Project ID P511453)

02Project Background

The Government of Guinea has received World Bank financing for Phase 2 of the Guinea Electricity Access Scale Up Project. The objectives of the project are to increase grid and non-grid access to electricity services in selected areas and to improve the operational performance of the power utility. The project has four components, the first of which covers the reinforcement and expansion of grid access and the improvement of the commercial performance of EDG. It is implemented by Electricité de Guinée and the Ministry of Energy, with a commitment of USD 232.30 million comprising USD 132.30 million from IDA and USD 100 million from the European Investment Bank; it was approved by the Board on 30 June 2025, became effective on 30 March 2026 and closes on 30 June 2030. Its theme composition records 100 per cent for Energy Access-Electricity and 92 per cent for Enabling Renewable Energy.

This procurement round concerns the urban centre of Labe and its surrounding localities. Labe is the principal city of Middle Guinea; its existing 30 kV medium voltage and low voltage distribution networks require rehabilitation and reinforcement, while some households remain unconnected or unmetered. The notice defines the contract as the rehabilitation, reinforcement and extension of the existing distribution networks, together with new service connections and metering, in order to raise supply reliability and improve commercial management in the city.

The contract includes work at two substations: the rehabilitation of the existing 30/30 kV Pounthioun substation and the construction of a new 30 kV transit substation at Hamda. In both cases the core scope is the supply, installation and commissioning of 30 kV medium voltage switchgear and its connection to the overhead network, as ancillary elements of the distribution network rehabilitation.

03Scope of Work & Technical Specifications

ItemContent
30 kV Medium Voltage Trunk Lines105.83 km of overhead lines in Almelec conductor, cross-section 148 mm²
Underground Line1.5 km, cross-section 240 mm²
30 kV Medium Voltage Distribution Lines138.61 km of overhead lines in Almelec conductor, cross-section 54.6 mm²
Low Voltage Lines1,247.46 km of low voltage lines, including public lighting
Distribution Transformer Substations108 H61-type units and 63 H59-type units
Service Connections and Metering65,796 service connections with metering, comprising 43,680 new connections and 22,116 connections to be regularised
Pounthioun Substation RehabilitationRehabilitation of the 30/30 kV substation: supply, installation and commissioning of seven 30 kV medium voltage switchgear panels, including their connection to the overhead network
Construction of the Hamda Transit SubstationConstruction of a new 30 kV transit substation: civil construction of the substation building; supply of four 30 kV medium voltage switchgear panels connected to the overhead network; supply of auxiliary service equipment including auxiliary transformers and direct current supply systems
Contract DurationUp to 24 months from the effective date of the contract
← Swipe to view the full table →

04Key Commercial Terms

ItemContent
Bid SecurityUSD 1,000,000 or GNF 8,764,000,000
Tender Document FeeGNF 2,000,000 (approximately USD 230), non-refundable, paid as to 50 per cent to the Treasury, 30 per cent to the public procurement regulatory authority and 20 per cent by cheque to the project implementation unit
Payment MethodPayments are made under the World Bank Direct Payment disbursement method for investment project financing
Performance SecurityWorks contracts financed by the World Bank ordinarily require a performance security after contract signature, commonly at 10 per cent of the contract price
Advance PaymentSuch works contracts ordinarily provide for a mobilisation advance against an advance payment guarantee, recovered in instalments as works progress
Defects Liability PeriodWorks contracts ordinarily include a defects liability period, commonly 12 months after completion
InsuranceWorks contracts ordinarily require the contractor to carry works all-risks insurance and third party liability insurance
Bid ValidityInternational tenders of this type ordinarily require bids to remain valid for 120 to 180 days from the submission deadline
Beneficial Ownership DisclosureAs required by the World Bank Procurement Regulations, the successful bidder must complete the beneficial ownership disclosure form at the contract award stage
← Swipe to view the full table →

05Bidder Qualification Requirements

01
Eligible Bidders
Open to bidders from eligible countries as defined in the World Bank Procurement Regulations
02
Design and Construction Capability
Bidders must be able to design, supply equipment for, construct, test and commission 30 kV medium voltage and low voltage distribution networks
03
Track Record
Evidence of constructing and commissioning overhead and underground lines and distribution transformer substations at the same voltage level and of comparable scale is ordinarily required
04
Key Personnel and Equipment
Bidders must provide suitably qualified key personnel and construction plant for medium voltage network works, together with personnel and equipment schedules
05
Financial Capability
Bidders must demonstrate financial capability commensurate with the contract and submit the financial documents required by the bidding document
06
Exclusion
Bidders must not appear on the World Bank listing of ineligible firms or on any official sanctions list
07
Bid Composition
The technical and financial envelopes are submitted separately sealed; at bid opening only the technical envelope is opened publicly, while the financial envelope remains sealed until the second public opening

06Key Milestones

8 Sep 2026
Notice Issued and Published
10 Nov 2026 at 10:30 (GMT)
Submission Deadline
10 Nov 2026 at 11:00 (GMT)
Bid Opening (Technical Envelope Opened Publicly)

07Evaluation Criteria

Technical and Non-price Evaluation60%
  • Distribution network design and construction methodology
  • qualifications of key personnel and the proposed construction plant
  • track record in network works at the same voltage level
  • quality, safety and environmental management arrangements
  • responsiveness of the bid to the technical requirements of the bidding document
Price Evaluation40%
  • The evaluated price after arithmetic correction and a completeness check of the bills of quantities
  • review of abnormally low prices and unbalanced pricing
  • reasonableness of the itemised pricing for lines, transformer substations and service connections
Contact Us
Room 1602, Tower D, Xiamen Sea World, Xiamen, China