01Project Overview
Project Name
Niger State Solar Energy Development Project — construction and installation of the 100 MW Maikunkele solar PV power generation plant and construction of grid interconnection and evacuation infrastructure
Tender Reference
Financing No. NGA1063; Lot 1 — NSSEP/WKS/ICB/26/01/Lot 1; Lot 2 — NSSEP/WKS/ICB/26/01/Lot 2
Country
Nigeria — Maikunkele, Bosso Local Government Area, Niger State
Project Type
Renewable power generation and grid infrastructure (solar PV plant with interconnection and evacuation works)
Contracting Authority
Niger State Government of the Federal Republic of Nigeria, acting through the Project Management Unit of the Niger State Solar Energy Development Project, with the project office at the New Niger Development Project (NNDP) office complex, opposite Keystone Bank, Bosso Road, Minna, Niger State
Procurement Method
International Competitive Bidding (ICB-Open) with prequalification as the current stage, conducted under the IsDB Guidelines for the Procurement of Goods, Works and Related Services (April 2019 edition, revised February 2023)
Contract Type
Civil works contracts, awarded and implemented separately for each lot
Source of Funds
Islamic Development Bank instalment sales financing of USD 150 million, financing No. NGA-1063
Lot Structure
Lot 1 — construction and installation of the 100 MW Maikunkele solar PV power generation plant
Lot 2 — construction of grid interconnection and evacuation infrastructure at Maikunkele
Project Components
A — solar PV power generation; B — grid interconnection and evacuation infrastructure; C — design and supervision consultancy; D — project management; E — project financial audit; F — Contingency Emergency Response Component (CERC)
Next Step
Following prequalification, the invitation to bid is expected to be issued in January 2027
02Project Background
The Federal Government of Nigeria enacted the Climate Change Act in 2021 and committed at COP26 to reaching carbon neutrality by 2060, subsequently publishing the Energy Transition Plan, which identifies power, transport, oil and gas, cooking, and industry as the five priority sectors for emission reduction. In the power sector, the plan's decarbonisation pathway centres on expanding solar generation and progressively replacing diesel and petrol self-generation, while gas provides transitional baseload capacity and grid capability to absorb renewable generation is upgraded in parallel. The project is located in Niger State, in north-central Nigeria, and forms part of the country's addition of new solar generation capacity in the power sector.
Nigeria's power system has long faced the twin constraints of insufficient generation capacity and limited transmission and distribution capability, with a large share of industrial, commercial and household demand met by diesel or petrol self-generation, and insufficient transmission corridor capacity has become a principal bottleneck for bringing new generation capacity into service. The procurement for this project separates the construction of the solar PV plant from the grid interconnection and evacuation infrastructure into two independent lots, so that generation-side works and connection and evacuation works advance in parallel and new capacity is not delayed by inadequate grid access.
The project is financed by the Islamic Development Bank through instalment sales financing under financing No. NGA-1063 for USD 150 million, covering solar PV power generation, grid interconnection and evacuation infrastructure, design and supervision consultancy, project management, project financial audit, and a contingency emergency response component. The Islamic Development Bank published the General Procurement Notice for the project on its procurement website on 26 July 2026, and the Niger State Government subsequently issued the Invitation for Prequalification, including Addendum No. 1, in September 2026 to prequalify international contractors for the civil works in the two lots.
03Scope of Work & Technical Specifications
| Item | Content |
|---|
| Lot 1 Scope | Construction and installation of the Maikunkele solar PV power generation plant with a capacity of 100 MW, comprising the civil works, erection and commissioning of the generation facilities and their associated systems |
| Lot 2 Scope | Construction of the grid interconnection and evacuation infrastructure at Maikunkele, comprising the works required to connect the plant to the grid and evacuate its output |
| Installed Capacity | 100 MW |
| Site | Maikunkele, Bosso Local Government Area, Niger State, Nigeria |
| Procurement Stage | Prequalification. Only prequalified applicants proceed to the subsequent International Competitive Bidding stage |
| Document Language | The prequalification documents are issued in English and applications are prepared in English |
| Inspection and Enquiries | Eligible applicants may inspect the prequalification documents and obtain further information at the project office during office hours from 09:00 to 17:00 |
| Submission Method | Applications are submitted in sealed hard-copy envelopes, clearly marked with the lot applied for (Lot 1, Lot 2 or both); electronic bidding is not permitted and late applications are rejected |
← Swipe to view the full table →
04Key Commercial Terms
| Item | Content |
|---|
| Contract Type | Civil works contracts awarded and implemented separately per lot, administered under the IsDB general conditions for works |
| Source of Financing | IsDB instalment sales financing under financing No. NGA-1063 for USD 150 million; part of the proceeds is applied by the Federal Government of Nigeria to payments under this contract |
| Tender Document Fee | Non-refundable prequalification document fee of NGN 250,000 or USD 200 |
| Payment Route | Payment is made by direct transfer or bank draft; the receiving accounts are held in the name of the Niger State Government (NNDP Project Account) at Zenith Bank, in naira and in US dollars respectively |
| Bid Security | Bid security is not ordinarily required at the prequalification stage; the requirement is set out with the bidding documents at the subsequent bidding stage |
| Performance Security | Performance security is ordinarily required from the successful bidder in works contracts of this type, typically at a percentage of the contract price and valid until the end of the defects liability period |
| Advance Payment | Advance payment arrangements, supported by an advance payment guarantee, are common in works contracts procured under international competitive bidding; the percentage and amortisation method are set out in the bidding documents |
| Insurance and Taxes | Contractors are ordinarily required to take out works all-risks and third-party liability insurance and to bear the taxes and duties applicable under Nigerian law |
← Swipe to view the full table →
05Bidder Qualification Requirements
01Eligible Source
Open to eligible applicants from IsDB member countries as defined in the IsDB Procurement Guidelines; firms and their affiliates that do not meet those requirements are not eligible
02Legal Status
Applicants must be legally incorporated contractors holding the qualifications and licences required to carry out solar PV plant and transmission works at the project site
03Financial Standing
Audited financial statements demonstrating the financial capacity and access to funds required for the lot applied for
04Relevant Experience
A track record as main contractor on solar PV plants or transmission infrastructure of comparable scale, supported by contract or completion evidence
05Technical and Managerial Capability
Deployment of qualified project, construction and technical managers together with site quality, safety and environmental personnel
06Obtaining the Prequalification Documents
Applicants must submit a written request to the contracting authority and pay the non-refundable document fee, or obtain the documents electronically against evidence of payment
07Application Requirements
Applications must be delivered in sealed hard-copy envelopes clearly marked with the lot applied for; electronic bidding is not permitted and late applications are rejected
06Key Milestones
26 Jul 2026
General Procurement Notice Issued
7 Sep 2026
Invitation for Prequalification Issued
13 Oct 2026
Submission Deadline and Bid Opening
Submission by 11:00 local time; public opening at 11:30 local time on the same day
Submission Cut-off and Opening Time
January 2027
Invitation to Bid (Expected)
07Evaluation Criteria
Technical Evaluation55%
- Works contracts procured under international competitive bidding are ordinarily assessed by weighting the technical and commercial parts separately. The technical part typically covers:
- Construction method and organisation for solar PV plants and transmission works of comparable scale
- Qualifications and deployment of the project manager and key personnel
- Construction plant, testing equipment and labour resources
- Track record and performance on works of comparable scale
Commercial Evaluation35%
- The commercial assessment ordinarily centres on the bid price and its completeness, typically covering:
- Level of the bid price
- Completeness and arithmetical check of the priced bid
- Responsiveness to the payment terms, programme and security arrangements
Execution and Safety Capability10%
- Evaluation of works contracts of this type ordinarily also covers execution and safety capability:
- Site organisation and temporary facilities
- Occupational health, safety and environmental controls
- Local resource mobilisation and logistics arrangements