Morocco is one of North Africa's fastest-growing wind markets, targeting 52% of installed power capacity from renewables by 2030. The site lies in the northern coastal mountains with annual average wind speeds above 8.5 m/s, offering strong capacity factors.
Wind measurement (no fewer than 24 months of data), land acquisition and the grid connection framework agreement are complete. The employer uses pre-qualification to select contractors capable of complex-terrain erection and local content delivery.
| Item | Content |
|---|---|
| Scope of Work | Turbine supply and transport, foundations, erection, access roads and crane pads, 220 kV substation, 25 km overhead transmission line, SCADA, commissioning and 5-year O&M |
| Wind Turbine Generators | ≥ 4.8 MW per unit, 155–165 m rotor, IEC 61400-1 certified, Class S / IIA suitability |
| Corrosion & Climate Adaptation | Corrosion protection of at least C4 (C5-M for coastal), suitable for 0–45 °C and dusty conditions |
| Grid Compliance | Compliance with the ONEE grid code: low-voltage ride-through, reactive power control, active power/frequency response and forecasting interface |
| Substation & Collection | 33 kV collector system and 220 kV substation (main transformers, GIS, protection and telecoms) |
| Civil Works & Logistics | Mountain road upgrade and new access roads, blade and nacelle transport solution, crane pads and heavy-haul permits |
| O&M Service | 5-year full-scope O&M with ≥ 97% availability guarantee, including spare parts, remote monitoring and annual major component maintenance |
| Environment & Social | Bird and bat monitoring, noise control, construction-phase ecological protection and community engagement plan |
| Item | Content |
|---|---|
| Bid Bond | USD 800,000 or equivalent bank guarantee in MAD |
| Performance Bond | 10% of contract price, on-demand guarantee |
| Advance Payment | 15% of contract price against an equal advance payment guarantee |
| Progress Payment | Milestone payments for supply, foundations, erection and commissioning |
| Retention | 5% withheld per payment, released on provisional acceptance and finally on expiry of warranty |
| Warranty & Availability | 5-year turbine warranty; ≥ 97% availability guarantee; energy yield guaranteed on a P90 basis |
| Insurance | CAR/EAR, cargo, third-party liability and O&M liability insurance by the contractor |
| Delay Liquidated Damages | 0.08% of contract price per day, capped at 8% |
| Local Content | Local content ≥ 30%; local procurement, employment and skills transfer plans required |
| Dispute Resolution | ICC arbitration, Moroccan law governs |
Up to 5% bonus for a complete and verifiable local content plan
Highest combined score wins; price is not the sole determining factor