The UAE has adopted a Net Zero 2050 strategy and Dubai targets 25% clean energy generation by 2030. Rooftop PV on industrial and logistics parks is a low-cost, fast-track delivery route.
The employer intends to lock in long-term EPC capacity through a framework and release orders in batches over three years. Contractors must hold Dubai local contracting credentials, be experienced in roof waterproofing and structural safety, and be able to work without interrupting factory operations.
| Item | Content |
|---|---|
| Scope of Work | Roof survey and structural load verification, design, supply, installation, grid connection application, commissioning, training and 10-year system warranty |
| PV Modules | N-type bifacial modules ≥ 580 Wp, efficiency ≥ 22%, salt-mist and PID resistant |
| Mounting Structure | Aluminium clamp-type mounting, non-penetrating in principle; where penetration is required, waterproofing and a 10-year warranty must be provided |
| Inverters | String inverters with module-level monitoring, designed for dusty and high-temperature conditions (derating at 50 °C ambient) |
| Grid Connection | 400 V / 11 kV connection with bi-directional metering, anti-islanding protection and interface switchgear per DEWA requirements |
| O&M Provisions | Remote monitoring platform with string-level alarms; optional 5-year O&M (cleaning, IR inspection, performance reporting) |
| Safety & Compliance | Compliance with Dubai Civil Defence requirements and local working-at-height regulations |
| Item | Content |
|---|---|
| Bid Bond | USD 150,000 bank guarantee |
| Performance Bond | 10% of each call-off order value |
| Advance Payment | No advance payment |
| Progress Payment | Monthly measurement of completed works; retention released on acceptance |
| Retention | 10% withheld per payment; 5% released on grid connection acceptance, 5% on expiry of warranty |
| Warranty | 10-year system warranty, 25-year module linear performance warranty, 10-year inverter warranty |
| Price Adjustment | Unit rates fixed for the framework term; adjusted per site at call-off stage |
| Insurance & Labour | Contractor bears third-party liability and construction insurance, labour visas and employment compliance |
| Delay Liquidated Damages | 0.2% of order value per day per site, capped at 10% |
| Dispute Resolution | DIFC arbitration, UAE law governs |
Top three bidders enter the framework; call-off share allocated by ranking
Each site is re-tendered among framework members; lowest compliant offer wins