Saudi Vision 2030 targets 50% of electricity from renewables by 2030, with solar PV and storage as the core delivery route. The project is located in the Red Sea Economic Zone, supplying clean power to the new city and its industrial loads while providing peaking capacity and enabling renewable curtailment relief for the grid.
Land allocation, grid connection consent and environmental permits are in place. The works are procured as a single design–supply–construct–commission–energise package. Contractors must demonstrate GW-scale integrated PV and electrochemical storage delivery capability and commit to local content (IKTVA).
| Item | Content |
|---|---|
| Scope of Work | Detailed design, equipment supply, civil works, installation and commissioning, grid connection tests, training and 2-year warranty support |
| PV Modules | N-type bifacial glass-glass modules ≥ 620 Wp, efficiency ≥ 22.5%, 25-year linear performance warranty |
| Mounting Structure | Single-axis trackers, sand-proof design, survival wind speed ≥ 45 m/s, 25-year structural warranty |
| Inverters | String inverters ≥ 300 MWac, max. efficiency ≥ 98.5%, with active and reactive power control |
| Battery Energy Storage | LFP liquid-cooled containerised system, 150 MWh / 75 MW, ≥ 6,000 cycles @90% DoD, incl. PCS, EMS and BMS |
| Substation & Grid Connection | 33 kV collector system, 380 kV substation extension and grid connection line |
| Control System | SCADA and EMS platform supporting remote dispatch, AGC/AVC and power forecasting interface |
| Civil Works & Ancillary Facilities | Access roads, fencing and security, met stations, spare parts store and O&M offices |
| Applicable Standards | IEC, IEEE and SASO standards, the Saudi grid code and NFPA 855 for BESS fire safety |
| Item | Content |
|---|---|
| Bid Bond | USD 1,200,000 bank guarantee, valid 180 days |
| Performance Bond | 10% of contract price, unconditional on-demand guarantee |
| Advance Payment | 10% of contract price against an equal advance payment guarantee |
| Progress Payment | Monthly milestone payments for design, supply, erection and commissioning |
| Acceptance & Retention | Cumulative release up to 95% on provisional acceptance, 5% on expiry of warranty |
| Warranty / Defects Liability | 24 months for the plant, 25-year module linear warranty, 10 years or 6,000 cycles for BESS |
| Insurance | CAR/EAR, third-party liability and marine cargo insurance by the contractor |
| Delay Liquidated Damages | 0.1% of contract price per day, capped at 10% |
| Dispute Resolution | LCIA arbitration seated in London, English law governs |
| Taxes & Duties | Contractor bears 20% corporate income tax in KSA and import customs duties |
| Local Content | IKTVA local content ≥ 40%, with preference for local civil works and services |
Bidders scoring below 60 on technical are not admitted to commercial evaluation
Highest combined score wins; the employer reserves the right not to award or to split the award