UN Procurement — Request for Quotation (RFQ)

Construction of a Solar-Powered Borehole and Connection to the Facilities of the Ponvogo Agricultural Plot, Cote d'Ivoire

Ref.UNDP-CIV-00502,2Issued2026-09-16Deadline2026-10-05
Ponvogo, Cote d'Ivoire
Site
45-day works period
Contract Duration
Borehole construction and connection of irrigation facilities
Contract Nature
2026-10-05 13:00 (New York time)
Bid Deadline

01Project Overview

Project Name
Construction of a solar-powered borehole and its connection to the facilities of the Ponvogo agricultural plot
Reference
UNDP request for quotation reference UNDP-CIV-00502 (amendment 2)
Country
Republic of Cote d'Ivoire
Contracting Authority
United Nations Development Programme, Cote d'Ivoire Country Office (UNDP-CIV)
Procurement Method
Request for Quotation (RFQ), submitted online through the UNDP Quantum supplier portal
Site
Ponvogo agricultural plot, Cote d'Ivoire
Contract Duration
45 days from notification of the service order to provisional acceptance
Amendment
The notice has been amended: the site visit attestation requirement was removed, the technical specifications were updated, and the type of hydraulic works approval issued by the National Drinking Water Office (ONEP) was clarified
Source
UNDP procurement notices portal, reference UNDP-CIV-00502,2, contracting authority UNDP Cote d'Ivoire, published 16 Sep 2026, verified 2 Oct 2026: https://procurement-notices.undp.org/view_negotiation.cfm?nego_id=49740
Background Sources
National Electricity Sector Regulatory Authority of Cote d'Ivoire (ANARE-CI), whose website records that the authority regulates the electricity sector and publishes the institutional framework, legislation and regulatory decisions of the sector: https://www.anare.ci/

02Project Background

The National Electricity Sector Regulatory Authority of Cote d'Ivoire (ANARE-CI) is the regulator of the electricity sector in Cote d'Ivoire. Its website publishes the institutional framework, legislative texts and regulatory decisions of the sector, covering generation, transmission, distribution and consumer relations. In the field of agricultural water use and irrigation, solar-powered pumping is an increasingly adopted abstraction method for agricultural plots, substituting for diesel pump sets where grid access is insufficient.

This request for quotation is issued by the UNDP Cote d'Ivoire Country Office for the construction of a solar-powered borehole at the Ponvogo agricultural plot and its connection to the irrigation facilities of the plot. The notice states that the works period is 45 days from notification of the service order to provisional acceptance, and that quotations must be submitted online through the UNDP Quantum supplier portal. The solicitation documents comprise the invitation letter, the RFQ instructions and data sheet, the technical specifications, the offer submission form and the bill of quantities and estimate. The notice also arranges a site visit which is recommended but not mandatory, held on 22 September 2026 at 10:00 at the Ponvogo site. Following the amendment, the site visit attestation requirement was removed, the technical specifications were updated and it was clarified that the hydraulic works approval issued by the National Drinking Water Office (ONEP) is required.

03Scope of Work & Technical Specifications

ItemContent
Main WorksConstruction of a solar-powered borehole at the Ponvogo agricultural plot and connection of the borehole to the irrigation facilities of the plot
SitePonvogo, Cote d'Ivoire
Contract Duration45 days from notification of the service order to provisional acceptance
Solicitation DocumentsInvitation letter, RFQ instructions and data sheet, Annex 1 technical specifications, Annex 2 offer submission form, Annex 3 bill of quantities and estimate
Technical SpecificationsThe technical requirements for borehole completion, the pumping and solar power supply configuration, and the piping and connection arrangements are set out in Annex 1 technical specifications
Site VisitArranged for 22 Sep 2026 at 10:00 at the Ponvogo site; not mandatory but recommended, at the bidder's own cost
SubmissionSubmitted online through the UNDP Quantum supplier portal
← Swipe to view the full table →

04Key Commercial Terms

ItemContent
Quotation BasisTechnical and financial offers are prepared on the Annex 2 offer submission form and the Annex 3 bill of quantities and estimate, and submitted online by the date and time specified
Submission PlatformThe UNDP Quantum supplier portal; suppliers must register and subscribe to the negotiation on the platform
Works Period45 days from notification of the service order to provisional acceptance
Payment and WarrantyWorks contracts of this kind usually provide for payment in instalments against progress milestones, and commonly provide for provisional and final acceptance together with a defect liability period
Amendment ManagementThe buyer issues amendments and clarifications through the messaging function of the portal; suppliers subscribed to the negotiation receive notifications of changes
← Swipe to view the full table →

05Bidder Eligibility Requirements

01
Platform Registration
Bidders must register on the UNDP Quantum supplier portal or use an existing profile, and subscribe to this negotiation following the user guide
02
Hydraulic Works Approval
Bidders must hold the hydraulic works approval issued by the National Drinking Water Office (ONEP)
03
Submission Documents
Bidders must submit the offer on the document set listed in the invitation letter, including the Annex 2 offer submission form, the Annex 3 bill of quantities and estimate, and the supporting documents required by the technical specifications
04
Site Visit
The site visit is recommended but not mandatory, so that the offer can be prepared with full knowledge of the site conditions
05
Compliance
Bidders must comply with the UN Supplier Code of Conduct; UNDP does not charge any fees at any stage of its procurement processes

06Key Milestones

16 Sep 2026
Notice Published
22 Sep 2026, 10:00 at the Ponvogo site
Site Visit
5 Oct 2026, 13:00 (New York time)
Submission Deadline
45 days from the service order to provisional acceptance
Works Period
Contact Us